Dept. of Trans. PROGRESS Serial No. Contract No. 25-232-13-58 08-1N4704 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 77% Location: Federal Project: 08-VAR NONE Progress payment No. 006 Payment period ending: 08-20-25 SELECT ELECTRIC INC 1700 E VIA BURTON ANAHEIM CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,913,811.85 340,423.35 2. a. Extra Work 144,947.75 20,246.49 b. Adustment Comp. -68,046.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,990,713.09 360,669.84 5. Mobilization 255,544.00 0.00 6. Total Work Completed 2,246,257.09 7. Deductions -15,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,231,257.09 360,669.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 360,669.84