Dept. of Trans. PROGRESS Serial No. Contract No. 23-114-20-44 08-1N5804 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 100% Location: Federal Project: 08-SBD-15-173.7/181.1 NONE Progress payment No. 004 Payment period ending: 04-20-23 LAS VEGAS PAVING CORP 4420 S DECATUR BLVD LAS VEGAS NV 89103 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 933,545.22 171,298.20 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 933,545.22 171,298.20 5. Mobilization 6. Total Work Completed 933,545.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 933,545.22 171,298.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 171,298.20