Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-14-33 08-1N7004 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 68% Location: Federal Project: 08-SBD-15-R17.7 NONE 08-SBD-15-R19.2 Progress payment No. 003 Payment period ending: 03-20-25 LAMASSU UTILITY SERVICES INC 3193 ENTERPRISE CT LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 474,979.94 69,568.73 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 474,979.94 69,568.73 5. Mobilization 6. Total Work Completed 474,979.94 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 469,979.94 69,568.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,568.73