Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-245-13-40 08-1N9604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-VAR NONE Progress payment No. 006 Payment period ending: 06-02-25 KANAAN CONSTRUCTION INC 5040 HEINTZ ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 909,766.12 5,550.00 2. a. Extra Work 42,737.79 6,622.22 b. Adustment Comp. 10,458.88 10,458.88 3. Materials on Hand 4. Earned Subject to Retention 962,962.79 22,631.10 5. Mobilization 46,000.00 0.00 6. Total Work Completed 1,008,962.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,008,962.79 22,631.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,631.10