Dept. of Trans. PROGRESS Serial No. Contract No. 25-108-10-30 08-1N9704 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 18% Location: Federal Project: 08-RIV-215-R9.0/R38.0 NONE Progress payment No. 001 Payment period ending: 04-20-25 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 202,800.00 202,800.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 202,800.00 202,800.00 5. Mobilization 6. Total Work Completed 202,800.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 202,800.00 202,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,800.00