Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-10-20 08-1N9704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 08-RIV-215-R9.0/R38.0 NONE Progress payment No. 004 Payment period ending: 07-20-25 KANAAN CONSTRUCTION INC 5040 HEINTZ ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 478,700.00 10,020.00 2. a. Extra Work 2,991.62 2,991.62 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 481,691.62 13,011.62 5. Mobilization 6. Total Work Completed 481,691.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 481,691.62 13,011.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,011.62