Dept. of Trans. PROGRESS Serial No. Contract No. 24-234-19-30 08-1P1304 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 9% Location: Federal Project: 08-VAR NONE Progress payment No. 001 Payment period ending: 08-20-24 PAVE-TECH INC 3043 HARDING ST CARLSBAD CA 92008 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 724,457.50 724,457.50 2. a. Extra Work b. Adustment Comp. 7,868.00 7,868.00 3. Materials on Hand 4. Earned Subject to Retention 732,325.50 732,325.50 5. Mobilization 280,868.45 280,868.45 6. Total Work Completed 1,013,193.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,013,193.95 1,013,193.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,013,193.95