Dept. of Trans. PROGRESS Serial No. Contract No. 26-169-08-00 08-1P6604 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 97% Location: Federal Project: 08-VAR NONE Progress payment No. 004 Payment period ending: 02-24-26 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 615,420.59 0.00 2. a. Extra Work 22,308.95 22,308.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 637,729.54 22,308.95 5. Mobilization 40,300.00 0.00 6. Total Work Completed 678,029.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 678,029.54 22,308.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,308.95