Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-08-14 08-1P8604 PROGRESS PAYMENT VOUCHER %complete: %time: 5% 100% Location: Federal Project: 08-SBD-18-17.6/17.9 NONE Progress payment No. 001 Payment period ending: 03-20-24 RIVERSIDE CONSTRUCTION CO INC 4225 GARNER RD RIVERSIDE CA 92501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 89,241.33 89,241.33 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 89,241.33 89,241.33 5. Mobilization 6. Total Work Completed 89,241.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 89,241.33 89,241.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,241.33