Dept. of Trans. PROGRESS Serial No. Contract No. 05-144-13-18 08-2015U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 08-SBD-60-R4.5/R8.7 Federal Project: 08-SBD-60-R6.3/R7.5 ACNH-P060(106) 08-SBD-60-R7.5/R8.4 Progress payment No. 59 Payment period ending: 05-20-05 ULICO CASUALTY CO 2040 MAIN ST SUITE 300 IRVINE CA 92614 Escrow No. 01287 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,531,411.80 7,500.00 2.a. Extra Work 182,836.78 0.00 b. Adjustment Comp. 11,622.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,725,870.82 7,500.00 5. Mobilization 65,000.00 0.00 6. Total Work Completed 1,790,870.82 7. Deductions -84,350.00 -6,650.00 8. a.Contract Retentions -86,293.54 -375.00 b. Unsatisfactory Prog. -2,064.34 -375.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,618,162.94 100.00 10. Reduction Amt to Escrow 11. Payment to Escrow 86,290.00 12. Net Pymt. this Estimate 100.00