Dept. of Trans. PROGRESS Serial No. Contract No. 03-204-08-08 08-204314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 27% 08-SBD-15-7.2/10.3 Federal Project: 08-SBD-30-R10.0/R13.7 ACIM-X071(42) Progress payment No. 06 Payment period ending: 07-18-03 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02040 Total Estimate This Estimate 1. Contract Itms Without Mobil. 629,337.10 436,663.10 2.a. Extra Work 63,661.34 58,107.58 b. Adjustment Comp. 21,521.00 21,521.00 3. Materials on Hand 4. Earned Subject to Retention 714,519.44 516,291.68 5. Mobilization 45,600.00 21,600.00 6. Total Work Completed 760,119.44 7. Deductions 8. a.Contract Retentions -56,338.76 -36,515.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 703,780.68 501,375.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 501,375.70