Dept. of Trans. PROGRESS Serial No. Contract No. 09-057-12-54 08-204324 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 08-SBD-210-9.4/11.0 Federal Project: NONE Progress payment No. 07 Payment period ending: 02-20-09 J M A CONSTRUCTION COMPANY 6143 HOPE ST SIMI VALLEY, CA 93063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 615,933.04 174,515.00 2.a. Extra Work 11,159.69 11,159.69 b. Adjustment Comp. 25,036.75 13,554.75 3. Materials on Hand 4. Earned Subject to Retention 652,129.48 199,229.44 5. Mobilization 65,600.00 0.00 6. Total Work Completed 717,729.48 7. Deductions -166,200.00 -118,600.00 8. a.Contract Retentions -32,606.47 -9,961.47 b. Unsatisfactory Prog. -28,260.89 -9,961.47 c. Reduction after 95% Comp. 9. Total pay to Contractor 490,662.12 60,706.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,706.50