Dept. of Trans. PROGRESS Serial No. Contract No. 10-328-10-25 08-227004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 76% 08-SBD-18-44.2/44.7 Federal Project: ACST-X071(53) PACB-X071(53) RSTP-X071(53) Progress payment No. 22 Payment period ending: 11-19-10 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,208,708.00 2,009,572.00 2.a. Extra Work 514,890.94 33,818.80 b. Adjustment Comp. 12,565.81 0.00 3. Materials on Hand 55,289.66 -220,304.69 4. Earned Subject to Retention 24,791,454.41 1,823,086.11 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 27,736,164.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,791,454.41 1,823,086.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,823,086.11