Dept. of Trans. PROGRESS Serial No. Contract No. 06-082-09-10 08-279004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 13% 08-SBD-15-40.5/ .0 Federal Project: ACIM-015-1(222) G-015-1(222) Progress payment No. 04 Payment period ending: 03-20-06 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,132.50 222,304.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 371,132.50 222,304.90 5. Mobilization 71,250.00 0.00 6. Total Work Completed 442,382.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 442,382.50 222,304.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,304.90