Dept. of Trans. PROGRESS Serial No. Contract No. 01-205-10-03 08-307404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-RIV-15-45.3/45.8 Federal Project: NONE Progress payment No. 14 Payment period ending: 07-20-01 REYCO EROSION CONTROL 7030 HAWARDEN DR RIVERSIDE CA 92506 Escrow No. 01569 Total Estimate This Estimate 1. Contract Itms Without Mobil. 195,770.00 1,500.00 2.a. Extra Work 14,000.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 209,770.00 1,500.00 5. Mobilization 7,000.00 0.00 6. Total Work Completed 216,770.00 7. Deductions 8. a.Contract Retentions -10,488.50 -75.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 206,281.50 1,425.00 10. Reduction Amt to Escrow 11. Payment to Escrow 10,300.00 12. Net Pymt. this Estimate 1,425.00