Dept. of Trans. PROGRESS Serial No. Contract No. 03-174-11-22 08-307404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 08-RIV-15-45.3/45.8 Federal Project: NONE Progress payment No. 34 Payment period ending: 06-17-03 REYCO EROSION CONTROL 7030 HAWARDEN DR RIVERSIDE CA 92506 Escrow No. 01569 Total Estimate This Estimate 1. Contract Itms Without Mobil. 229,220.00 2,175.00 2.a. Extra Work 16,181.74 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 245,401.74 2,175.00 5. Mobilization 7,000.00 0.00 6. Total Work Completed 252,401.74 7. Deductions -14,250.00 -1,000.00 8. a.Contract Retentions -12,270.09 -108.75 b. Unsatisfactory Prog. -1,706.58 -108.75 c. Reduction after 95% Comp. 9. Total pay to Contractor 224,175.07 957.50 10. Reduction Amt to Escrow 11. Payment to Escrow 12,270.00 12. Net Pymt. this Estimate 957.50