Dept. of Trans. PROGRESS Serial No. Contract No. 08-330-08-20 08-333904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-15-41.7/42.4 Federal Project: DPIL-061(25) Progress payment No. 19 Payment period ending: 11-20-08 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA ROAD RIVERSIDE CA 925092405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,055,523.88 2,956.00 2.a. Extra Work 191,819.34 15,811.06 b. Adjustment Comp. 23,547.01 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,270,890.23 18,767.06 5. Mobilization 530,000.00 0.00 6. Total Work Completed 5,800,890.23 7. Deductions -20,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,780,890.23 13,767.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,767.06