Dept. of Trans. PROGRESS Serial No. Contract No. 03-238-11-09 08-334834 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 73% 08-RIV-91-20.3/21.6 Federal Project: 08-RIV-60-11.5/12.1 ACNH-X065(75) Progress payment No. 10 Payment period ending: 08-20-03 SEMA CONSTRUCTION INC 2 SOUTH POINTE DRIVE STE 295 LAKE FOREST CA 92630 Escrow No. 02048 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,706,955.35 596,238.13 2.a. Extra Work 446,744.05 195,378.75 b. Adjustment Comp. 588.20 588.20 3. Materials on Hand 25,539.10 -39,877.40 4. Earned Subject to Retention 10,179,826.70 752,327.68 5. Mobilization 140,000.00 0.00 6. Total Work Completed 10,294,287.60 7. Deductions -16,081.80 0.00 8. a.Contract Retentions -508,991.34 -37,616.39 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,794,753.56 714,711.29 10. Reduction Amt to Escrow 11. Payment to Escrow 508,990.00 12. Net Pymt. this Estimate 714,711.29