Dept. of Trans. PROGRESS Serial No. Contract No. 03-358-09-17 08-334834 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 80% 08-RIV-91-20.3/21.6 Federal Project: 08-RIV-60-11.5/12.1 ACNH-X065(75) Progress payment No. 14 Payment period ending: 12-19-03 SEMA CONSTRUCTION INC 2 SOUTH POINTE DRIVE STE 295 LAKE FOREST CA 92630 Escrow No. 02048 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,782,013.31 423,080.73 2.a. Extra Work 613,578.66 23,951.16 b. Adjustment Comp. 267,155.67 30,705.82 3. Materials on Hand 0.00 -17,492.02 4. Earned Subject to Retention 13,662,747.64 460,245.69 5. Mobilization 140,000.00 0.00 6. Total Work Completed 13,802,747.64 7. Deductions -16,081.80 0.00 8. a.Contract Retentions -683,137.38 -23,012.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,103,528.46 437,233.41 10. Reduction Amt to Escrow 11. Payment to Escrow 683,130.00 12. Net Pymt. this Estimate 437,233.41