Dept. of Trans. PROGRESS Serial No. Contract No. 05-238-08-10 08-334844 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 37% 08-RIV-215-R37.7/43.9 Federal Project: 08-RIV-91-20.3/21.6 ACNH-215-1(219) 08-RIV-60-11.5/13.7 I-215-1(219) ACNH-X065(80) Progress payment No. 21 Payment period ending: 08-19-05 WASHINGTON GROUP INTERNATIONAL INC OBAYASHI CORPORATION A JOINT VENTURE P O BOX 600 HIGHLAND CA 92346 Escrow No. 02171 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,145,609.81 3,603,646.86 2.a. Extra Work 2,754,601.94 568,153.53 b. Adjustment Comp. 4,739,884.50 199,863.04 3. Materials on Hand 2,422,304.38 -135,276.33 4. Earned Subject to Retention 54,062,400.63 4,236,387.10 5. Mobilization 17,425,911.70 0.00 6. Total Work Completed 69,066,007.95 7. Deductions -258,383.85 82,946.27 8. a.Contract Retentions -3,561,719.23 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 67,668,209.25 4,319,333.37 10. Reduction Amt to Escrow 11. Payment to Escrow 3,561,710.00 12. Net Pymt. this Estimate 4,319,333.37