Dept. of Trans. PROGRESS Serial No. Contract No. 13-144-12-58 08-334864 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-RIV-215-43.1/43.9 Federal Project: 08-RIV-60-11.5/12.2 NONE 08-RIV-91-20.3/21.6 Progress payment No. 24 Payment period ending: 05-20-13 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,433,625.53 1,820.00 2.a. Extra Work 92,060.77 0.00 b. Adjustment Comp. -17,979.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,507,706.80 1,820.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 3,597,706.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,597,706.80 1,820.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,820.00