Dept. of Trans. PROGRESS Serial No. Contract No. 13-025-11-49 08-334874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 68% 08-RIV-215-39.7/43.0 Federal Project: NONE Progress payment No. 07 Payment period ending: 01-18-13 YAKAR 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 466,804.35 74,475.57 2.a. Extra Work 16,115.68 13,235.02 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 482,920.03 87,710.59 5. Mobilization 57,000.00 0.00 6. Total Work Completed 539,920.03 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 534,920.03 82,710.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,710.59