Dept. of Trans. PROGRESS Serial No. Contract No. 13-085-10-38 08-334874 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 84% 08-RIV-215-39.7/43.0 Federal Project: NONE Progress payment No. 09 Payment period ending: 03-20-13 YAKAR 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 795,303.75 155,404.99 2.a. Extra Work 46,791.02 3,625.28 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 842,094.77 159,030.27 5. Mobilization 60,000.00 0.00 6. Total Work Completed 902,094.77 7. Deductions -7,500.00 -2,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. -35,917.48 -15,903.03 c. Reduction after 95% Comp. 9. Total pay to Contractor 858,677.29 140,627.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,627.24