Dept. of Trans. PROGRESS Serial No. Contract No. 14-148-16-24 08-334884 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-RIV-215-38.6/39.7 Federal Project: NONE Progress payment No. 20 Payment period ending: 05-21-14 CLEAN CUT LANDSCAPE 8406 N AMRSTRONG AVENUE CLOVIS, CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 273,184.26 1,568.50 2.a. Extra Work 77,019.37 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 350,203.63 1,568.50 5. Mobilization 32,500.00 0.00 6. Total Work Completed 382,703.63 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 382,703.63 1,568.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,568.50