Dept. of Trans. PROGRESS Serial No. Contract No. 18-115-14-24 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 12% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 005 Payment period ending: 04-20-18 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,995,495.34 3,572,155.12 2. a. Extra Work 81,668.59 16,500.00 b. Adustment Comp. 3. Materials on Hand 491,000.00 491,000.00 4. Earned Subject to Retention 11,568,163.93 4,079,655.12 5. Mobilization 7,812,098.00 0.00 6. Total Work Completed 18,889,261.93 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,370,261.93 4,079,655.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,079,655.12