Dept. of Trans. PROGRESS Serial No. Contract No. 18-234-14-03 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 27% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 009 Payment period ending: 08-20-18 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,787,689.02 5,535,453.92 2. a. Extra Work 91,551.62 0.00 b. Adustment Comp. 199,980.00 0.00 3. Materials on Hand 1,321,747.00 257,729.00 4. Earned Subject to Retention 33,400,967.64 5,793,182.92 5. Mobilization 14,842,986.20 3,124,839.20 6. Total Work Completed 46,922,206.84 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,223,953.84 8,918,022.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,918,022.12