Dept. of Trans. PROGRESS Serial No. Contract No. 18-325-13-04 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 38% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 012 Payment period ending: 11-20-18 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,707,717.15 13,354,231.57 2. a. Extra Work 106,730.42 0.00 b. Adustment Comp. 208,760.23 0.00 3. Materials on Hand 401,856.00 0.00 4. Earned Subject to Retention 65,425,063.80 13,354,231.57 5. Mobilization 14,842,986.20 0.00 6. Total Work Completed 79,866,194.00 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 80,248,050.00 13,354,231.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,354,231.57