Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-14-41 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 49% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 016 Payment period ending: 03-20-19 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,713,901.67 5,401,641.37 2. a. Extra Work 295,082.17 63,330.36 b. Adustment Comp. 217,129.43 0.00 3. Materials on Hand 1,347,630.00 576,458.00 4. Earned Subject to Retention 92,573,743.27 6,041,429.73 5. Mobilization 15,624,196.00 0.00 6. Total Work Completed 106,850,309.27 7. Deductions -22,100.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 108,175,839.27 6,041,429.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,041,429.73