Dept. of Trans. PROGRESS Serial No. Contract No. 19-267-13-30 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 71% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 022 Payment period ending: 09-20-19 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92064 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 129,754,512.46 3,364,467.91 2. a. Extra Work 439,293.93 22,103.09 b. Adustment Comp. 316,897.53 -25,239.80 3. Materials on Hand 4. Earned Subject to Retention 130,510,703.92 3,361,331.20 5. Mobilization 15,624,196.00 0.00 6. Total Work Completed 146,134,899.92 7. Deductions -33,150.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 146,101,749.92 3,351,331.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,351,331.20