Dept. of Trans. PROGRESS Serial No. Contract No. 20-022-15-58 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 85% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 026 Payment period ending: 01-20-20 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92064 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 143,446,477.42 3,122,534.79 2. a. Extra Work 483,127.75 18,620.23 b. Adustment Comp. 367,866.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 144,297,471.68 3,141,155.02 5. Mobilization 15,624,196.00 0.00 6. Total Work Completed 159,921,667.68 7. Deductions -173,150.00 -60,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 159,748,517.68 3,081,155.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,081,155.02