Dept. of Trans. PROGRESS Serial No. Contract No. 20-204-15-30 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 93% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 032 Payment period ending: 07-20-20 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92064 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 152,453,341.84 2,199,126.29 2. a. Extra Work 7,579,623.34 2,638,172.28 b. Adustment Comp. -423,568.45 -1,366,833.02 3. Materials on Hand 4. Earned Subject to Retention 159,609,396.73 3,470,465.55 5. Mobilization 15,624,196.00 0.00 6. Total Work Completed 175,233,592.73 7. Deductions -83,150.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 175,150,442.73 3,460,465.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,460,465.55