Dept. of Trans. PROGRESS Serial No. Contract No. 20-237-14-39 08-347704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 97% Location: Federal Project: 08-SBD-58-R0.0/R12.9 NH Progress payment No. 033 Payment period ending: 08-20-20 KIEWIT INFRASTRUCTURE WEST CO. 12700 STOWE DR #180 POWAY CA 92064 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 152,841,424.90 388,083.06 2. a. Extra Work 9,149,117.43 1,569,494.09 b. Adustment Comp. -423,441.43 127.02 3. Materials on Hand 4. Earned Subject to Retention 161,567,100.90 1,957,704.17 5. Mobilization 15,624,196.00 0.00 6. Total Work Completed 177,191,296.90 7. Deductions -93,150.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 177,098,146.90 1,947,704.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,947,704.17