Dept. of Trans. PROGRESS Serial No. Contract No. 03-267-14-35 08-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 48% 08-SBD-15-41.9/70.6 Federal Project: ACIM-015-1(215) ACNH-015-1(215) I-015-1(215) Progress payment No. 19 Payment period ending: 09-19-03 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01917 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,043,549.29 3,651,285.28 2.a. Extra Work 1,074,712.12 114,719.42 b. Adjustment Comp. 638,402.01 82,394.31 3. Materials on Hand 360,949.73 36,013.20 4. Earned Subject to Retention 50,117,613.15 3,884,412.21 5. Mobilization 9,800,000.00 490,000.00 6. Total Work Completed 59,556,663.42 7. Deductions -1,448,746.03 -13,867.84 8. a.Contract Retentions -2,505,880.66 -194,220.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 55,962,986.46 4,166,323.76 10. Reduction Amt to Escrow 11. Payment to Escrow 2,505,880.00 12. Net Pymt. this Estimate 4,166,323.76