Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 04-183-15-31 08-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-15-41.9/70.6 Federal Project: ACIM-015-1(215) ACNH-015-1(215) I-015-1(215) Progress payment No. 32 Payment period ending: 06-16-04 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 01917 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,625,585.39 35,813.75 2.a. Extra Work 2,595,154.19 66,476.30 b. Adjustment Comp. 906,174.15 2,817.01 3. Materials on Hand 362,885.19 0.00 4. Earned Subject to Retention 74,489,798.92 105,107.06 5. Mobilization 9,800,000.00 0.00 6. Total Work Completed 83,926,913.73 7. Deductions -88,799.40 0.00 8. a.Contract Retentions -3,724,489.95 -5,255.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 80,476,509.57 99,851.70 10. Reduction Amt to Escrow 11. Payment to Escrow 3,600,000.00 12. Net Pymt. this Estimate 99,851.70