Dept. of Trans. PROGRESS Serial No. Contract No. 05-026-10-53 08-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 08-SBD-15-41.9/70.6 Federal Project: ACIM-015-1(215) ACNH-015-1(215) I-015-1(215) Progress payment No. 40 Payment period ending: 01-20-05 E L YEAGER CONSTRUCTION COMPANY INC 1995 AGUA MANSA RD RIVERSIDE CA 925092405 Escrow No. 01917 Total Estimate This Estimate 1. Contract Itms Without Mobil. 89,354,236.03 1,083,633.99 2.a. Extra Work 4,362,584.00 149,805.29 b. Adjustment Comp. 2,092,575.20 266,656.24 3. Materials on Hand 78,621.55 -43,586.25 4. Earned Subject to Retention 95,888,016.78 1,456,509.27 5. Mobilization 9,800,000.00 0.00 6. Total Work Completed 105,609,395.23 7. Deductions -159,702.93 -7,949.34 8. a.Contract Retentions -4,794,400.84 -72,825.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 100,733,913.01 1,375,734.47 10. Reduction Amt to Escrow 11. Payment to Escrow 4,600,000.00 12. Net Pymt. this Estimate 1,375,734.47