Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-216-15-18 08-3555U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-41.9/70.6 Federal Project: ACIM-015-1(215) ACNH-015-1(215) I-015-1(215) Progress payment No. 44 Payment period ending: 07-01-05 E L YEAGER CONSTRUCTION COMPANY INC 1995 AGUA MANSA RD RIVERSIDE CA 925092405 Escrow No. 01917 Total Estimate This Estimate 1. Contract Itms Without Mobil. 91,093,808.99 234,616.88 2.a. Extra Work 6,183,300.18 1,434,619.26 b. Adjustment Comp. 2,603,572.68 400,177.69 3. Materials on Hand 0.00 -63,182.05 4. Earned Subject to Retention 99,880,681.85 2,006,231.78 5. Mobilization 9,800,000.00 0.00 6. Total Work Completed 109,680,681.85 7. Deductions -2,570,052.85 -2,410,000.00 8. a.Contract Retentions -4,893,722.50 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 4,893,722.50 4,893,722.50 9. Total pay to Contractor 107,110,629.00 4,489,954.28 10. Reduction Amt to Escrow -4,893,720.00 -4,893,720.00 11. Payment to Escrow 4,893,720.00 12. Net Pymt. this Estimate -403,765.72