Dept. of Trans. PROGRESS Serial No. Contract No. 19-143-16-26 08-3555V4 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 87% Location: Federal Project: 08-SBD-15-42.5/46.0 NHPI-015-1(237) 146E STPL-N620-8(29) Progress payment No. 042 Payment period ending: 05-20-19 AMES CONSTRUCTION INC 2000 AMES DR BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,556,990.63 451,993.85 2. a. Extra Work 4,183,487.28 -1,273.68 b. Adustment Comp. 993,897.95 159,598.83 3. Materials on Hand 230,778.90 -15,482.29 4. Earned Subject to Retention 48,965,154.76 594,836.71 5. Mobilization 6,900,000.00 0.00 6. Total Work Completed 55,634,375.86 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 55,854,154.76 594,836.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 594,836.71