Dept. of Trans. PROGRESS Serial No. Contract No. 20-147-11-32 08-3555V4 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 08-SBD-15-42.5/46.0 NHPI-015-1(237) 146E STPL-N620-8(29) Progress payment No. 055 Payment period ending: 05-20-20 AMES CONSTRUCTION INC 2000 AMES DR BURNSVILLE MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 66,424,075.18 155,770.00 2. a. Extra Work 6,533,614.95 272,334.98 b. Adustment Comp. 2,207,975.65 27,025.16 3. Materials on Hand 4. Earned Subject to Retention 75,165,665.78 455,130.14 5. Mobilization 6,900,000.00 0.00 6. Total Work Completed 82,065,665.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 82,065,665.78 455,130.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 455,130.14