Dept. of Trans. PROGRESS Serial No. Contract No. 01-085-16-19 08-3564U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 33% 08-RIV-71-2.6/G3.0 Federal Project: ACNH-X065(63) Progress payment No. 08 Payment period ending: 03-20-01 LEHIGH CONSTRUCTION COMPANY 714 SOUTH PLYMOUTH BLVD LOS ANGELES CA 90005 Escrow No. 01527 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,137,743.08 76,816.50 2.a. Extra Work 205,441.79 -1,981.63 b. Adjustment Comp. -2,125.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,341,059.87 74,834.87 5. Mobilization 47,500.00 0.00 6. Total Work Completed 1,388,559.87 7. Deductions -41,184.12 -19,204.12 8. a.Contract Retentions -113,734.26 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,233,641.49 55,630.75 10. Reduction Amt to Escrow 11. Payment to Escrow 113,730.00 12. Net Pymt. this Estimate 55,630.75