Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 01-219-13-54 08-359014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 89% 08-SBD-62-0.8/9.6 Federal Project: ACNH-P062(21) Progress payment No. 06 Payment period ending: 07-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01648 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,665,687.90 20,973.00 2.a. Extra Work 46,530.11 12,085.35 b. Adjustment Comp. 27,689.51 -9,449.73 3. Materials on Hand 4. Earned Subject to Retention 2,739,907.52 23,608.62 5. Mobilization 161,315.00 0.00 6. Total Work Completed 2,901,222.52 7. Deductions 8. a.Contract Retentions -136,995.38 -1,180.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,764,227.14 22,428.19 10. Reduction Amt to Escrow 11. Payment to Escrow 136,990.00 12. Net Pymt. this Estimate 22,428.19