Dept. of Trans. PROGRESS Serial No. Contract No. 19-086-07-27 08-368514 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 08-SBD-15-87.1/181.1 NONE Progress payment No. 021 Payment period ending: 03-20-19 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,663,764.42 3,500.00 2. a. Extra Work 584,894.82 74,180.25 b. Adustment Comp. 558,269.93 64,927.33 3. Materials on Hand 4. Earned Subject to Retention 33,806,929.17 142,607.58 5. Mobilization 3,217,592.75 0.00 6. Total Work Completed 37,024,521.92 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,004,521.92 132,607.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 132,607.58