Dept. of Trans. PROGRESS Serial No. Contract No. 04-239-15-52 08-370204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 50% 08-SBD-15-33.5/34.5 Federal Project: ACIM-015-1(217) ACIM-015-1(217) HP21-6208(5) Progress payment No. 10 Payment period ending: 08-20-04 YEAGER SKANSKA INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 02145 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,505,347.00 52,472.00 2.a. Extra Work 25,436.23 -1,036.23 b. Adjustment Comp. 1,836.30 0.00 3. Materials on Hand 61,212.86 61,212.86 4. Earned Subject to Retention 2,593,832.39 112,648.63 5. Mobilization 776,150.00 0.00 6. Total Work Completed 3,308,769.53 7. Deductions -205,565.87 -28,421.22 8. a.Contract Retentions -156,367.87 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,008,048.65 84,227.41 10. Reduction Amt to Escrow 11. Payment to Escrow 156,360.00 12. Net Pymt. this Estimate 84,227.41