Dept. of Trans. PROGRESS Serial No. Contract No. 05-082-08-59 08-370204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 76% 08-SBD-15-33.5/34.5 Federal Project: ACIM-015-1(217) ACIM-015-1(217) HP21-6208(5) Progress payment No. 17 Payment period ending: 03-18-05 YEAGER SKANSKA INC 1995 AGUA MANSA RD RIVERSIDE CA 925092405 Escrow No. 02145 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,400,969.54 332,254.00 2.a. Extra Work 90,205.83 10,894.11 b. Adjustment Comp. 1,836.30 0.00 3. Materials on Hand 42,662.43 -1,550.43 4. Earned Subject to Retention 4,535,674.10 341,597.68 5. Mobilization 817,000.00 40,850.00 6. Total Work Completed 5,310,011.67 7. Deductions 8. a.Contract Retentions -226,783.71 -17,079.89 b. Unsatisfactory Prog. -17,079.88 -17,079.88 c. Reduction after 95% Comp. 9. Total pay to Contractor 5,108,810.51 348,287.91 10. Reduction Amt to Escrow 11. Payment to Escrow 226,780.00 12. Net Pymt. this Estimate 348,287.91