Dept. of Trans. PROGRESS Serial No. Contract No. 05-026-10-53 08-371304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 71% 08-SBD-10-R24.2/R24.3 Federal Project: 08-SBD-215-4.2/4.4 NONE Progress payment No. 13 Payment period ending: 01-20-05 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02156 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,123,626.90 1,142,496.10 2.a. Extra Work 413,714.45 12,927.70 b. Adjustment Comp. 3. Materials on Hand 486,496.00 -715,022.00 4. Earned Subject to Retention 11,023,837.35 440,401.80 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 11,937,341.35 7. Deductions 8. a.Contract Retentions -551,191.87 -22,020.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,872,645.48 418,381.71 10. Reduction Amt to Escrow 11. Payment to Escrow 551,190.00 12. Net Pymt. this Estimate 418,381.71