Dept. of Trans. PROGRESS Serial No. Contract No. 07-333-10-57 08-374204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 15% 08-SBD-5718 Federal Project: NONE Progress payment No. 01 Payment period ending: 11-20-07 STEVENS CONSTRUCTION INC 530 WEST AVE L LANCASTER CA 93534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,770.00 34,770.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 34,770.00 34,770.00 5. Mobilization 6. Total Work Completed 34,770.00 7. Deductions 8. a.Contract Retentions -3,477.00 -3,477.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 31,293.00 31,293.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,293.00