Dept. of Trans. PROGRESS Serial No. Contract No. 08-239-10-52 08-375304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 28% 08-SBD-5724 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-08 STEVENS CONSTRUCTION INC 530 WEST AVENUE L LANCASTER CA 93534 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 158,866.60 112,189.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 158,866.60 112,189.30 5. Mobilization 6. Total Work Completed 158,866.60 7. Deductions 8. a.Contract Retentions -15,886.66 -11,218.93 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 142,979.94 100,970.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,970.37