Dept. of Trans. PROGRESS Serial No. Contract No. 08-115-15-56 08-3770U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 63% 08-SBD-5506 Federal Project: CMLN-6208(14) Progress payment No. 04 Payment period ending: 04-18-08 RIVERSIDE CONSTRUCTION COMPANY INC P O BOX 1146 RIVERSIDE CA 92502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,326,510.54 564,675.84 2.a. Extra Work 80,599.78 6,896.92 b. Adjustment Comp. 40,118.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,447,229.28 571,572.76 5. Mobilization 320,000.00 16,000.00 6. Total Work Completed 1,767,229.28 7. Deductions -41,765.90 -2,088.30 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,725,463.38 585,484.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 585,484.46