Dept. of Trans. PROGRESS Serial No. Contract No. 13-297-10-43 08-378704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 71% 08-SBD-62-142.2/142.9 Federal Project: STP-BRST(PP0) STP-BRST(PP0) BR-S95(A20) Progress payment No. 32 Payment period ending: 10-17-13 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,140,022.57 4,350.00 2.a. Extra Work 1,828,110.58 81,748.23 b. Adjustment Comp. 185,708.04 59,422.76 3. Materials on Hand 520,819.96 -14,400.00 4. Earned Subject to Retention 17,674,661.15 131,120.99 5. Mobilization 2,255,992.00 0.00 6. Total Work Completed 19,409,833.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,930,653.15 131,120.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 131,120.99