Dept. of Trans. PROGRESS Serial No. Contract No. 13-360-12-57 08-378704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 72% 08-SBD-62-142.2/142.9 Federal Project: STP-BRST(PP0) STP-BRST(PP0) BR-S95(A20) Progress payment No. 34 Payment period ending: 12-18-13 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,258,039.57 0.00 2.a. Extra Work 3,041,900.11 1,205,522.65 b. Adjustment Comp. 35,758.04 -149,950.00 3. Materials on Hand 827,089.96 -1,054,865.78 4. Earned Subject to Retention 19,162,787.68 706.87 5. Mobilization 2,255,992.00 0.00 6. Total Work Completed 20,591,689.72 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,418,779.68 706.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 706.87