Dept. of Trans. PROGRESS Serial No. Contract No. 15-238-16-04 08-383504 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 32% Location: Federal Project: 08-RIV-74-63.0 STP-P074(59) Progress payment No. 003 Payment period ending: 08-20-15 GRANITE CONSTRUCTION COMPANY 440 SOUTH MELROSE DRIVE 200 VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,312.10 149,530.00 2. a. Extra Work 4,357.66 883.11 b. Adustment Comp. 775.29 0.00 3. Materials on Hand 4. Earned Subject to Retention 333,445.05 150,413.11 5. Mobilization 147,000.00 49,000.00 6. Total Work Completed 480,445.05 7. Deductions -37,382.00 -37,382.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 443,063.05 162,031.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 162,031.11